TCN COMPLETES INSTALLATION OF 2NEW 60MVA POWER TRANSFORMERS IN UYO AND KANO
The Transmission Company of Nigeria TCN has completed the installation and commissioning into service, two brand new 60MVA 132/33kV power transformers in its transmission substations in Uyo and Kano and has also energized its Nsukka 30MVA transmission substation completed in 2016 that could not be energized then, due to way leave issues.
In a statement signed by the General Manager (Public Affairs) Mrs. Ndidi Mbah, TCN said that the brand new 60MVA 132/33kV power transformer in its Uyo transmission substation, was installed to replace the burnt 60MVA LEEC power transformer which caught fire in the substation last month. The 60MVA power transformer which was energized on 22nd March, 2018, increased the number of 60MVA power transformers in the substation to three and has equally increased the Uyo Substation capacity from 120MVA to 180MVA. The additional transformer capacity means improved power supply to distribution customers of Port-Harcourt DisCo in Uyo Oron, Mbo, Ikot-Ekpene Abak, Ethan, Airport and environs.
In the same vein, the capacity of Dan Agundi Substation, Kano State, has increased from 60MVA to 120MVA, with the successful installation of a brand new 60MVA power transformer in the substation. The transformer installation which was initially awarded to a contractor was taken over by TCN engineers, with a mandate to complete installation within two weeks.
The new Dan Agundi transformer TCN said, has been delivered and would be energized on Saturday, 24th March, after all the pre-commissioning tests have been completed. Once energized, electricity transmission to Kano Electricity Distribution Company for delivery to its customers in Kano would improve substantially.
The statement further revealed that the Nsukka 30MVA Transmission Station, Enugu State, was energized on the 20th of March, 2018. The substation which had been completed since 2016, was not operational because of Right of Way issues as well as court injunctions which stalled the stringing of the 132kV transmission line to the substation. However, with the intervention of the Enugu State Governor, Ifeanyi Ugwuanyi, the transmission line project was completed and energized. Nsukka and environs would experience more quality supply going forward.