South Africa: Portfolio Committee on Electricity and Energy Welcomes Improved Monitoring Systems to Address Water Pollution at Kusile Power Station

The Portfolio Committee on Electricity and Energy has welcomed Eskom’s revised water management plans at Kusile Power Station following a court ruling directing the utility to address water pollution and environmental non-compliance at the facility.
Yesterday the committee conducted an oversight visit to the power station, where management briefed members on its revised water management action plans after the Supreme Court of Appeal’s August 2026 judgment ordering Eskom and relevant state regulators to address water pollution and environmental compliance failures at Kusile.
Senior management at the plant informed the committee that the action plan reviews existing and potential pollution sources, strengthens water quality monitoring programmes, incorporates audit findings and areas for improvement, and introduces corrective measures aimed at improving downstream water quality.
“We welcome compliance with the court orders, which was our primary focus during today’s visit. The filing of the action plans is encouraging progress,” said Committee Chairperson Ms Zamakhanyase Khanyase.
“The committee welcomes the revised water monitoring programme and the improved technologies outlined to us. I believe we should not find ourselves in this position again, where positive work is overshadowed by matters of this nature. It is a clear lesson that we should not wait for court intervention, as that creates an impression of reluctance to act voluntarily,” Ms Khanyase said.
She added that the committee looks forward to the implementation of the plans and will closely monitor progress to ensure Kusile and Eskom meet their set deadlines.
“We are encouraged by the comprehensiveness of your responses. This has been a productive engagement that strengthens our oversight work,” she said.
The committee also noted Kusile’s efforts to reduce emissions and urged the station to sustain improvements in air quality management and emissions compliance.
Today the committee will visit Hendrina and Arnot power stations to receive updates on the possible decommissioning of the facilities. The committee seeks to ensure that any decommissioning takes place within the Just Energy Transition framework, with programmes in place to support affected workers and communities fairly.
Distributed by APO Group on behalf of Republic of South Africa: The Parliament.